I’m with Jeff. Note it and move on. On a side note, How do you know it was an electrician? Couldn’t it have been the Butler, in the Study, with a knife?
Let’s see… One 8’ or 10’ Rod equals two 4’ or 5’ Rods when cut in half!
Once driven in the ground, the AHJ will never know the contractor is a cheap biotch!!
Around here, our AHJs want to see the clamp, so they are always a couple of inches above grade. I rarely look close enough to see saw marks on the top, so good catch by Kent. Of course, is it a 9’ that had two inches cut off?
Yes, after you cut in make sure that you smash it 100 times with a lump hammer. No one will be able to tell that it was cut if you do it right. Don’t ask how I know this.
It’s just my opinion but ground rods are a bit of a joke and their actual usefulness is constantly debated by electricians. Pound in 7 1/2’ and hit rock then what? Cannot pull it back out, can’t pound in the last 6", send the helper to get the angle grinder.
The exception also allows it to be buried full length in a 30" trench. Around here, they’ll allow any excess to be bent over and buried so that the entire length of the rod is fully in contact with soil.
Yes you’re correct, if it cannot be driven down at 45° or less then you can bury it horizontally. The way the requirement is written you first have to try and go down. Before I dug a trench 30" deep and 8’ long I would switch to a plate electrode.
I like your idea of bending it over if you get almost all of the way in and cannot go any further. Given the limited usefulness of ground rods the bend over method should be good enough.