# Rafter bracing

**URL:** <https://forum.nachi.org/t/rafter-bracing/105708>\
**Category:** Structural Inspections\
**Created:** [April 17, 2016, 9:32pm UTC](https://forum.nachi.org/t/rafter-bracing/105708 "2016-04-17T21:32:48Z")\
**Posts on this page:** 4\
**Page:** 1

<div class="post-metadata">

**Author:** ![belliott2](https://avatars.discourse-cdn.com/v4/letter/b/a9a28c/32.png) [@belliott2](https://forum.nachi.org/u/belliott2)\
**Post date:** [April 17, 2016, 9:32pm UTC](https://forum.nachi.org/t/rafter-bracing/105708/1 "2016-04-17T21:32:48Z")

</div>

Howdy!

Newbie with some more rafter bracing questions. Saw this in a new construction house and was concerned there was no support underneath (load bearing wall, etc) this brace. Is this correct with only a partially doubled joist? Odd that if you look at photo #2 the purlin braces are on a large beam, but this single brace is just stuck in the corner of the attic entrance framework with a doubled joist. Thanks!

 ![RafterBrace1.jpg](https://global.discourse-cdn.com/internachi/original/3X/9/3/931cc1b1ad02f44818a6ee584bdbc917e6d49a33.jpeg)

 ![RafterBrace1.jpg](https://global.discourse-cdn.com/internachi/original/3X/9/3/931cc1b1ad02f44818a6ee584bdbc917e6d49a33.jpeg)

 ![RafterBrace1.jpg](https://global.discourse-cdn.com/internachi/original/3X/9/3/931cc1b1ad02f44818a6ee584bdbc917e6d49a33.jpeg)

 ![Rafterbrace2.jpg](https://global.discourse-cdn.com/internachi/original/3X/0/8/08e45572a65ee7f352b13eca8a82a3813d01e747.jpeg)

---

<div class="post-metadata">

**Author:** ![twitt](https://sea2.discourse-cdn.com/internachi/user_avatar/forum.nachi.org/twitt/32/58462_2.png) [@twitt](https://forum.nachi.org/u/twitt)\
**Post date:** [April 18, 2016, 7:49am UTC](https://forum.nachi.org/t/rafter-bracing/105708/2 "2016-04-18T07:49:19Z")

</div>

> [@belliott2](#):
>
> Howdy!
> 
> Newbie with some more rafter bracing questions. Saw this in a new construction house and was concerned there was no support underneath (load bearing wall, etc) this brace. Is this correct with only a partially doubled joist? Odd that if you look at photo #2 the purlin braces are on a large beam, but this single brace is just stuck in the corner of the attic entrance framework with a doubled joist. Thanks!

Hi Bryan,

This house is, of course, under construction and the braces look temporary.  
It’s a bit difficult to tell from pictures what is going on, is this a hip roof?  
It might be that they are going to install knee walls at some point.

---

<div class="post-metadata">

**Author:** ![cevans](https://sea2.discourse-cdn.com/internachi/user_avatar/forum.nachi.org/cevans/32/244194_2.png) [@cevans](https://forum.nachi.org/u/cevans)\
**Post date:** [April 18, 2016, 11:07pm UTC](https://forum.nachi.org/t/rafter-bracing/105708/3 "2016-04-18T23:07:35Z")

</div>

That’s not a temporary brace. It’s permanent strut with a stiffener supporting a splice in a hip rafter down to a double joist. I see no issue, though if I had my druthers it would go to a strongback. I wouldn’t comment on it.

---

<div class="post-metadata">

**Author:** ![belliott2](https://avatars.discourse-cdn.com/v4/letter/b/a9a28c/32.png) [@belliott2](https://forum.nachi.org/u/belliott2)\
**Post date:** [April 20, 2016, 5:06am UTC](https://forum.nachi.org/t/rafter-bracing/105708/4 "2016-04-20T05:06:05Z")

</div>

Thanks for the help! Yes, under construction, hip roof.