Main panel when a house generator is installed

Your lack of understanding what a service is hampering your understanding of the correct NEC terminology. The transfer switch becomes the service. Look at the definition of an electrical service…it is not how the transfer switch accomplishes the changeover.

1 Like

The panel containing the service disconnect, ‘even if that is the only breaker,’ is the considered to be the main service panel. Any panel downstream are sub-panels/remote distribution panels, and subject to the rules governing them.
Would this be appropriate wording in the case?

I think that you’re pretty close. Here are some NEC definitions that may help.

Service Equipment.
The necessary equipment, consisting of a circuit breaker(s) or switch(es) and fuse(s) and their accessories, connected to the serving utility and intended to constitute the main control and disconnect of the serving utility.

Service.
The conductors and equipment connecting the serving utility to the wiring system of the premises served.

Service Conductors.
The conductors from the service point to the service disconnecting means.

1 Like

Here’s what I get. Thank you by the way.

NEC-National Electric Code as “the conductors and equipment for delivering energy from the electricity supply system to the wiring system of the premises served ”.

The video is great… it is very clear and simple to understand. And it clearly answers the OP’s question.

I am glad I could help!
:innocent:

I agree it does show one way of using a generator and an ATS but the video has a few code violations in it. The biggest violation being running the service conductors in the same raceway as the feeder conductors. My advice is thread lightly when viewing these videos as many of the electrical installation videos shown on YouTube depict things that are not code complaint.

3 Likes

The biggest issue is he said it will get inspected at the end. So people assume it was done correctly even more so. And the POCO guy didn’t care or know any better, either. This is how this type of mistakes are made and should, ideally, be discovered by a competent home inspector, hopefully before any fires.

1 Like

My reaction was to the point of the switch becoming the “service”, and the service panel now referred to as a subpanel. It makes sense and was very clear. I’m seeing more and more of these installations and appreciate someone bringing it up.

Yup that was my point. It was a good video because it showed various components of a backup generator system with an ATS but without some kind of vetting I would not use YouTube or Google searches as a tool for gathering the correct information unless the source is known to be reliable.

2 Likes