Student Discussion: 2023 Florida Residential Building Code Course

This thread on the InterNACHI® Inspection Community Forum is dedicated to students enrolled in InterNACHI’s free, online “2023 Florida Residential Building Code Course.”

Enrolled students may ask questions and join the discussion about this course.

The thread is monitored according to our guidelines.

2 Likes

Starting the Course is there any recomendations that could be provided

There are several changes with soffits and more. The major changes in the 2020 FBC regarding roof sheathing thickness requirements remained the same, there was a minor change in the roof sheathing fastener requirements. The 2023 FBC defers to the 2020 NEC which has several updates. Also not sure if it’s covered in the course, there was a new provision regarding EV charging provisions in the 2023 FBC Energy Conservation.

FBC Energy Conservation would also be a good thing to be familiar with.

Starting the 2023 Florida Residential Building Code Course.

Starting Today!

Am I seeing a typo or what: Which type of door is NOT permitted between a garage and a bedroom?

Any door is permitted as long as it is self-closing.
Solid or honeycomb-core steel door, 1 3/8 inches thick
20-minute fire-rated door
Solid wood door, 1 3/8 inches thick

My understanding is no door is permitted from a garage to a sleeping room/bedroom….

2 Likes

Another typo, I answered the question and it said I was wrong, did not know I had to pick the right one….lol, I knew it was 6 mil, just picked the wrong one..

What is the minimum thickness required for a polyethylene vapor retarder under a concrete slab-on-ground floor?

6 mil
6 mil
4 mil
2 mil

In which of the following situations is a vapor retarder NOT required under a concrete slab?

A heated basement.
A covered patio.
An unheated garage and a covered patio.

1 Like

Starting course today.

1 Like

Starting the course to continue with CE credits

1 Like