I know that a main panel in a bathroom is improper but how would you report in a narrative where the panel was there long before a toilet and sink were added? I would be grateful for some advice with the observation and an appropriate recommendation. Thanks,
Bob

Half bath.JPG

Half bath.JPG

I wouldn’t get into the dates of what was where first. No need too. Just report that the (OCPD) Over Current Protection Device is located in an area not approved. Recommend a qualified electrical contractor to relocate as needed. It will be cheaper than relocation/removal of the bathroom. Not sure in your area, but it most likely wasn’t permitted as it hasn’t been allowed since NEC 1993 240-24(e)

You cant have an electrical panel of any kind in a bathroom. Either bath needs to go or panel needs to be relocated.