Beam and support

Originally Posted By: smcintire
This post was automatically imported from our archived forum.



http://www.nachi.org/bbsystem/usrimages/more/P1010006.JPG ]


[ Image: http://www.nachi.org/bbsystem/usrimages/more/P10100071.JPG ]


Originally Posted By: jpeck
This post was automatically imported from our archived forum.



Steve,


Based on the non-stained areas, I'd guess that there used to be a different support there. Something with two underside supports and something on the side at the joint.


--
Jerry Peck
South Florida

Originally Posted By: kmcmahon
This post was automatically imported from our archived forum.



Girder joints over supports must be tied (IRC 502.9)



Wisconsin Home Inspection, ABC Home Inspection LLC


Search the directory for a Wisconsin Home Inspector

Originally Posted By: smcintire
This post was automatically imported from our archived forum.



Jerry and Kevin, thanks IRC 502.9 gives me what I was looking for.


Thanks as always


Originally Posted By: jpeck
This post was automatically imported from our archived forum.



kmcmahon wrote:
Girder joints over supports must be tied (IRC 502.9)


Huh?

(2003 IRC) R502.9 Fastening. Floor framing shall be nailed in accordance with Table R602.3(1). Where posts and beam or girder construction is used to support floor framing, positive connections shall be provided to ensure against uplift and lateral displacement.


--
Jerry Peck
South Florida

Originally Posted By: kmcmahon
This post was automatically imported from our archived forum.



Don’t kill the messenger…it’s noted in code check as 502.9



Wisconsin Home Inspection, ABC Home Inspection LLC